Marshfield Street Division has Closed N. Chestnut Avenue for Three-Tier Project
Tuesday, April 16th, 2024 -- 10:01 AM
The Marshfield Street Division closed N. Chestnut Ave. – W. Blodgett St. to W. Depot St. for the next 4-6 weeks.
This is a three-tier project.
- 1st tier will be on N. Chestnut Ave. from W. Blodgett St. to W. Arnold St.
- 2nd tier will be on N. Chestnut Ave. from W. Arnold St. to W. Depot St.
- 3rd tier will be on W. Depot St. from N. Central to W. Chestnut Ave.
This construction will consist of replacing the mainline sanitary sewer/sewer laterals. The Street Division will maintain access to the residents during the construction phase, with potential delays.
The detour will be:
Veterans Pkwy to N. Central Ave
Central Ave. to W. Doege St.
Oak Ave. to St. Joseph Ave.
St. Joseph Ave. to Veterans PkwyR
Regarding any questions or concerns, please get in touch with the Street Division at 715-486-2081 or by e-mail at [email protected].
Feel free to contact us with questions and/or comments.